TeraWulf expands Kentucky Power contract, doubles Muskie campus capacity to 1 GW
Bitget2026/10/05 12:15Terawulf executed an amended electric service agreement with Kentucky Power, raising contracted capacity at its Muskie Data Campus to 1 GW. Second 500 MW phase delivery moved up to 2029 from 2030, subject to Kentucky Public Service Commission sign-off. Initial 500 MW phase remains slated to start ramping in 2028. Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Terawulf Inc. published the original content used to generate this news brief via GlobeNewswire (Ref. ID: 202610050815PRIMZONEFULLFEED9839327) on October 05, 2026, and is solely responsible for the information contained therein.
- Terawulf executed an amended electric service agreement with Kentucky Power, raising contracted capacity at its Muskie Data Campus to 1 GW.
- Second 500 MW phase delivery moved up to 2029 from 2030, subject to Kentucky Public Service Commission sign-off.
- Initial 500 MW phase remains slated to start ramping in 2028.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Only 1.45 Billion Shiba Inu (SHIB) Burned in 24 Hours Hints at Reversal
Viral Altcoin Defies Market Slumber With 53% Surge, BTC Calms at $83K: Weekend Watch

Global Bank Stocks Sink as Bond Losses Top $326 Billion: Is Another SVB Coming?