Hydro One seeks Ontario regulator approval for CAD 1.3 billion North Shore Link transmission line
Reuters2026/09/11 21:21- Hydro One filed a joint application with Ontario’s energy regulator to build the North Shore Link 230-kV transmission line.
- Project targets a new connection from Mississagi TS near Wharncliffe to Third Line TS in Sault Ste. Marie.
- Investment sized at $ 1.3 billion; in-service date targeted for 2029.
- Plan includes upgrades at Mississagi TS, expansion at Algoma TS; Third Line TS upgrades to be managed by Hydro One Sault Ste. Marie.
- Nine First Nations may take up to a 50% equity stake in the transmission line component under the partnership model.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
EdiliziAcrobatica announces shareholder meeting notice

Storage Giant Offers Huge Bonuses Again: Micron Awards Up to 68 Months’ Bonus
Micron Technology has announced record-breaking bonuses for its employees in Taiwan, ranging from 35 to 68 months’ salary, with a minimum cash compensation of 1.7 million New Taiwan dollars. However, the Taoyuan union, representing about two-thirds of Micron’s workers in Taiwan, has refused to accept the offer, insisting that 15% of operating profits be included in the bonus distribution and maintaining the threat of a strike.